Stora Enso in Fors have now completed the test run period of four large PME 7204 Super Silent evaporative cooling towers at their waste water treatment plant. And so far, the equipment has done their job well according to Stora Ensos Project Manager.

The installation and start up was performed earlier this spring although some of the work surrounding the units needed further completion. Now the fixed protective railings have been put in place as well as the special fire protection walls.

The project is a typical example where we have acted as technical advisors with site specific customization for best solution. Both with focus on minimized total installation cost and present/future capacity redundancy.

You can read more about our cooling towers here, and if you want to know more please call or e-mail us today!